File #: 24-789    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 11/6/2024 In control: Board of Commissioners
On agenda: 12/2/2024 Final action:
Title: Task Order Amendment - SCADA Master Plan
Attachments: 1. Task Order Amendment 04
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE:title
Task Order Amendment - SCADA Master Plan
body
INFORMATION CONTACT:
John Shutak, Union County Water - Engineering, Director, 704-283-3651
ACTION REQUESTED:
Accept the scope of services as shown in the attached Amendment 04 to Task Order 2020-02 with HDR Engineering, Inc. of the Carolinas in the amount of $139,850, and authorize the County Manager to negotiate and execute an agreement substantially consistent with this agenda item.
PRIOR BOARD ACTIONS:
1) May 3, 2021, Regular Meeting, Agenda Item # 9 - Approved Task Order 2020-02 with HDR Engineering, Inc. of the Carolinas in the amount of $396,582.
2) June 19, 2023, Regular Meeting, Agenda Item # 23-389 - Approved Amendment 02 to Task Order 2020-02 with HDR Engineering, Inc. of the Carolinas in the amount of $48,199.
BACKGROUND:
The Capital Improvement Program, as adopted by the Board of County Commissioners, includes funding for the assessment, design, and replacement of System Control and Data Acquisition (SCADA) infrastructure. Master planning for SCADA system replacement, radio communications analysis (telemetry), and human machine interface (HMI) software acquisition activities have been completed as part of the overall SCADA project effort. The master plan identified projects for implementation grouped into three main categories (1) network architecture, (2) telemetry, and (3) replacement of remote terminal units (RTU's) and programmable logic controllers (PLC's). The design and construction of required improvements for the SCADA system computer network (network architecture) has been completed. The design for the telemetry system and RTU and PLC replacements has been completed and the project is presently under construction. Supporting these projects is the implementation and deployment of the new HMI software.

The deployment and implementation of the selected HMI software, VTScada, is largely complete including the development of the object library, graphic interface, and establishing conn...