Skip to main content
Union County Banner
 
The regular meeting of the Union County Board of Commissioners scheduled for Monday, February 2, 2026, will not be held out of an abundance of caution for public safety due to inclement weather.  All items on the agenda will move to the next regularly scheduled meeting on Tuesday, February 17, 2026.
 
Due to construction at the Union County Government Center, the primary entrance off Main Street Plaza is closed. Visitors should follow signage to the facility's temporary entrances. To learn more or to view a project map, visit ucgov.info/PardonOurProgress.  

File #: 24-644    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 9/6/2024 In control: Board of Commissioners
On agenda: 10/21/2024 Final action:
Title: 2025 Critical Intersection Design and Cost Estimate Study Planning Grant Application
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE:title

2025 Critical Intersection Design and Cost Estimate Study Planning Grant Application

body

INFORMATION CONTACT: 

Bjorn E. Hansen, Planning Department, Senior Planner - Long Range Planning, 704-283-3690

ACTION REQUESTED:

1) Authorize staff to submit a grant application to the Charlotte Regional Transportation Planning Organization (CRTPO), 2) upon award, authorize the County Manager to negotiate and execute agreements substantially consistent with this agenda item, and 3) upon award, recognize, receive, and appropriate funding to the Planning Department’s budget.

PRIOR BOARD ACTIONS:

September 18, 2023, Regular Meeting, Agenda Item # 23-623 - Approved 2023 Critical Intersection Analysis

BACKGROUND:

Union County advances intersections identified in its multiple Critical Intersection Analyses by applying for design and cost estimate planning grants through CRTPO. Union County has administered four of these grants since 2016, which have led to multiple funded and implemented intersection projects. Staff have coordinated with the NCDOT and local municipalities to identify five intersections from the 2023 Critical Intersection Analysis. If funded, the work would occur between July 2025 and June 2026. The five intersections, and the affected municipalities, are below:

                     New Town and Lester Davis (Wesley Chapel)

                     Old Charlotte Highway and Hayes/Faircroft (Indian Trail)

                     Unionville Indian Trail and Unionville Brief/CJ Thomas (Unionville)

                     Bragg and Lancaster (Monroe)

                     NC 84 and Willoughby

 

The estimated cost per intersection is $40,000, with a 20% match ($8,000) required per intersection. The total project cost would be $200,000, with Union County responsible for $24,000. The four municipalities would be responsible for $16,000.

FINANCIAL IMPACT: 

$24,000 in FY2026.