TITLE:title
Contract - Waxhaw South Sanitary Sewer Replacement & Rehabilitation Final Design
body
INFORMATION CONTACT:
John Shutak, Union County Water, Engineering Director, 704-283-3651
ACTION REQUESTED:
Authorize the County Manager to 1) negotiate and execute an agreement with WK Dickson & Co., LLC. d/b/a Ardurra Group North Carolina substantially consistent with this agenda item, 2) exercise any renewal or extension term options set forth in the Agreement, and 3) terminate the Agreement if deemed in the best interest of the County, each at the County Manager's discretion.
PRIOR BOARD ACTIONS:
1) March 1, 2021, Regular Meeting, Agenda Item #4 - Approved WK Dickson Task Order 2021-01 to complete an engineering condition assessment of the Septic Tank Effluent Gravity (STEG) wastewater collection system in Waxhaw.
2) March 20, 2023, Regular Meeting, Agenda Item #23-057 - Approved WK Dickson Task Order Task Order 2021-09 for engineering design services for Year 1 of the two year wastewater collection system replacement program.
BACKGROUND:
The Capital Improvement Plan (CIP) includes an annual allocation in the Wastewater Rehabilitation & Replacement Program to assess, prioritize, and rehabilitate/replace sanitary sewer collection system infrastructure. This project is Year 2 of a two-year rehabilitation project to replace the aged STEG wastewater collection system in Waxhaw. It will consist of the replacement of approximately 7,700 linear feet of 4-inch and 6-inch sewer pipe with 8-inch sewer mains on the south side of Highway 75 in downtown Waxhaw.
WK Dickson & Co., LLC. d/b/a Ardurra Group North Carolina has been selected to provide engineering services for Task Order 8678-05 - Waxhaw South Sanitary Sewer Replacement & Rehabilitation Final Design. WK Dickson & Co., LLC. d/b/a Ardurra Group North Carolina was chosen from a list of vendors previously selected from RFQ 2024-024 - Engineering Services for Water/Wastewater System Improvements to provide these se...
Click here for full text