File #: 26-147    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 2/26/2026 In control: Board of Commissioners
On agenda: 3/16/2026 Final action:
Title: Contract - JAARS Pump Station Replacement
Attachments: 1. Task Order 8679-02
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE:title

Contract - JAARS Pump Station Replacement 

body

INFORMATION CONTACT: 

John Shutak, Union County Water, Engineering Director, 704-283-3651

ACTION REQUESTED:

Authorize the County Manager to 1) negotiate and execute an agreement with Highfill Infrastructure Engineering, P.C. substantially consistent with this agenda item, 2) exercise any renewal or extension term options set forth in the Agreement, and 3) terminate the Agreement if deemed in the best interest of the County, each in the County Manager's discretion.

PRIOR BOARD ACTIONS:

None.

BACKGROUND:

The Capital Improvement Program for Union County Water (UCW), as adopted by the Board of County Commissioners, includes an annual allocation for the reconstruction and rehabilitation of wastewater pump stations within the sanitary sewer collection system. The Jungle Aviation and Radio Service (JAARS) Pump Station was identified for replacement in the UCPW Pump Station Assessment report dated March 15, 2018.

 

Highfill Infrastructure Engineering, P.C. has been selected to provide engineering design and bid services for Task Order 8679-02: JAARS Pump Station Replacement.  Highfill Infrastructure Engineering, P.C. was chosen from a list of vendors previously selected from RFQ 2024-021 - Engineering Services for Water and Wastewater System Improvements to provide these services for Union County Projects.

FINANCIAL IMPACT: 

The total cost of Task Order 8679-02 with Highfill Infrastructure Engineering, P.C. is $291,700.00. Sufficient funds are available within the adopted capital account 60185099 - JAARS Pump Station Replacement.