Title: FY 2025 Capital Project Ordinances - Union County Water Capital Projects
Attachments: 1. Capital Project Ordinance 174C, 2. Capital Project Ordinance 276B, 3. Capital Project Ordinance 246B, 4. Capital Project Ordinance 262A, 5. Capital Project Ordinance 281B, 6. Capital Project Ordinance 312E, 7. Capital Project Ordinance 313C, 8. Capital Project Ordinance 318B, 9. Capital Project Ordinance 325B, 10. Capital Project Ordinance 326D, 11. Capital Project Ordinance 328B, 12. Capital Project Ordinance 331B, 13. Capital Project Ordinance 334A, 14. Capital Project Ordinance 335B, 15. Capital Project Ordinance 354A, 16. Capital Project Ordinance 370, 17. Capital Project Ordinance 371, 18. Capital Project Ordinance 372, 19. Capital Project Ordinance 373, 20. Capital Project Ordinance 374, 21. Capital Project Ordinance 375, 22. Capital Project Ordinance 376, 23. Capital Project Ordinance 377
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE:title
FY 2025 Capital Project Ordinances - Union County Water Capital Projects
body
INFORMATION CONTACT:
Beverly Liles, Finance, Director, 704-283-3675; Amy McCaskill, UC Water - Business Operations, Director, 704-283-3508
ACTION REQUESTED:
Adopt the following capital project ordinances (CPOs):

CPO# Project Name(s)
174C 762 Zone Tank
246B Storage Tank Rehab, WWTP R&R, OC Expansion, 12 Mile Adm Building
262A Crooked Creek Admin Building
276B 853 West Zone Transmission Main
281B Yadkin Raw Water Intake and Pump Station
312E Water R&R
313C WW R&R, SCADA, Septic Tank Assessment, STEG Assessment Waxhaw
318B Indian Trail Tank #1
325B Collection System SSES and Rehab
326D Crooked Creek Interceptor Improvements Phase 2
328B Wastewater Pump Station Upgrades/Improvements
331B Grassy Branch WRF Expansion
334A Lower Crooked Creek Site B
335B Twelve Mile Creek WRF Expansion 7.5-9MGD
354A Short Water Line Extensions
370 821 Zone Providence Road BPS Supply Main
371 853 East Zone Transmission Main
372 Forest Park Pump Station Improvements
373 Risk and Resiliency Assessment
374 935 East Zone Tank
375 Catawba River Water Treatment Plant Expansion
376 880 Transmission Main
377 East Fork Interceptor Improvements
PRIOR BOARD ACTIONS:
1) June 17, 2024, Regular Meeting, Agenda Item # 24-404 - Adoption of FY 2025 Operating Budget
2) April 15, 2024, Regular Meeting, Agenda Item # 24-255 - UC Water CIP Workshop Follow up.
BACKGROUND:
CPOs 174C, 262A, 276B and 281B will reallocate funding sources on existing projects that are currently funded with revenue bond proceeds from the 2019A and 2021 Revenue Bond issuances. Reallocating the bond proceeds to the 853 West Zone Transmission Main project, which is nearly complete, will allow Finance to close out the construction fund bank accounts that remain open for unspent bond proceeds. This will mitigate any future arbitrage liability costs associated with the 2019A and 2021 Revenue Bonds.

All other CPO...

Click here for full text