Legislation Details

File #: 24-363    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 5/19/2024 In control: Board of Commissioners
On agenda: 6/3/2024 Final action:
Title: Government Center/Judicial Center Renovation - Recommend Construction Manager at Risk Delivery Method
Attachments: 1. Delivery Method Comparisons
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE:title
Government Center/Judicial Center Renovation - Recommend Construction Manager at Risk Delivery Method
body
INFORMATION CONTACT:
Christopher Boyd, Facilities Management, Director, 704-283-3868
ACTION REQUESTED:
Approve the use of the Construction Manager at Risk delivery method for the Government Center/Judicial Center Renovation project.
PRIOR BOARD ACTIONS:
None
BACKGROUND:
The Government Center/Judicial Center Renovation capital improvement project aims to address critical space needs for the court system and general government operations. It's part of the County's Capital Improvement Plan, with $5,447,419.00 approved and allocated in the FY2024 budget for preliminary design and cost analysis.
Driving factors include the need for additional courtrooms and modifications to existing ones to address current courtroom backlogs, accommodate specialized courtrooms, and develop new spaces for the Guardian Ad Litem and Public Defenders offices. The project entails renovating 38,965 gsf across both buildings, focusing on adding two courtrooms and renovating another. Additionally, space relocation and renovation are necessary within both buildings.
Per NCGS 143-128.1.e, Construction Management at Risk (CM@Risk) services may be used by the public entity only after the public entity has concluded that CM@Risk services is in the best interest of the project, and the public entity has compared the advantages and disadvantages of using the CM@Risk method for a given project in lieu of traditional delivery methods.
Facilities Management has evaluated the traditional Design-Bid-Build, Design-Build, and CM@Risk delivery methods. Based on current construction market conditions including ongoing inflation of construction input costs and continuing long lead times, the CM@Risk delivery method is proposed. This method offers many advantages including: quicker costing, scheduling analysis, flexible scoping, qualification-based contractor selection, pre-qualification ...

Click here for full text